JUNCTION LIGHTS PROBLEMS RESOLVED AT HERNE HILL

We have the following response from transport for London.We understand that continuing problems with a telephone connection linking the lights to the control centre caused the phasing to change and a delay in remedy.

Thank you for your emails of 15 and 30 May 2006, with regards to the above mentioned traffic signals.

I would firstly like to apologise for not replying sooner. I understand that the issue you have raised to do with the phasing of these signals has been an ongoing one, and as you have indicated has caused some considerable congestion.
Our signals engineers have been investigating the ongoing issues to do with these signals and on 30 May 2006 visited the site and resolved the problems that had caused the phasing to be out of kilter. I trust that you have observed a considerable improvement since that date.
Thank you again for your email(s). Please contact me if you require any further assistance.
Yours sincerely
Dominic Gibbins Surface Transport Communications